Day #189: Mitsubishi Heating & Lowering Of Curb Stones

Tiistaina 30. maaliskuuta 2010 · Marius

here we go with pics of MITSUBISHI ECODAN HEATING within technic room in the house. the unit has not yet completely installed. so we have one of the rare chances to see some pics of its interior.
finally also holes in ground done for house connection are closed. you can also see that curb stones had already been lowered.

2010-03-30_foto-2.jpg2010-03-30_foto.jpg2010-03-30_foto-3.jpg

Day #188: Mitsubishi Zubadan Heating & Copper Tubes

Maanantaina 29. maaliskuuta 2010 · Marius

hello, here we go with further pics shoot today. early in the morning folks of HUBERT NIEWELS arrived. the MITSUBISHI ECODAN HEATING splits up into two systems. the external unit has been installed, after carrying it below the house. this wasn’t fun, as it was raining during the morning. the internal unit will be installed tomorrow. you can also see the copper tubes in the sleeping room on where the JANSSEN FUSSBODENHEIZUNG aluminium wings will be placed within the next days.

2010-03-29_foto-7.jpg2010-03-29_foto-8.jpg2010-03-29_foto-9.jpg

Day #187: Floor Battens Preparation

Sunnuntaina 28. maaliskuuta 2010 · Marius

finally all rooms (except the children room) received their floor battens, so that peter is able install copper tubes for the special JANSSEN floor heating system tomorrow.

img_0747.jpgimg_0748.jpgimg_0749.jpg

Day #186: Technic Room & Floor Battens In Sleeping Room

Sunnuntaina 28. maaliskuuta 2010 · Marius

the sleeping room had been prepared with a vacuum cleaner job to receive its floor battens. here is an “before” and “after” view.

img_0738.jpgimg_0741.jpg

you can also see a new toy i used for fixing battens. as the battens are 45 mm, the OSB 22 mm and the battens below the OSB again 45 mm this special “john rambo signature edition” air nailer had been helpful. the unit can shoot special 90 mm nails.

img_0739.jpg

the technic room already received its floor in the area where the MITSUBISHI heating will arrive tomorrow.

img_0743.jpg

Day #185: Electrissity & Water In House Available

Perjantaina 26. maaliskuuta 2010 · Marius

since today the electrissity and water is available in the house.

as you can see, the water meter is still on zero. electrissity is something new (digital!)… and did show 1,0 kw/h.

img_0737.jpgimg_0732.jpg

i got to mention that we placed the very last piece of isolation today. finally! ;-)

Day #184: Pressure Drainage Installation

Perjantaina 26. maaliskuuta 2010 · Marius

this thursday the pressure drainage had been installed.

img_0727.jpg

oh… and i forgot to mention: since yesterday water is on the tube. on the right hand side your can see the control unit of the pressure drainage.

img_0728.jpgimg_0729.jpg

Day #182: House Connection Continues (On Our Ground)…

Perjantaina 26. maaliskuuta 2010 · Marius

here you can see the water tubes going into the house.

img_0713.jpgimg_0715.jpgimg_0718.jpg

Day #181: House Connection Continues …

Perjantaina 26. maaliskuuta 2010 · Marius

here you can see further pics of house installation. the grave down the street had already been closed again.

img_0710.jpgimg_0712.jpg

Day #179: Moving Wood

Perjantaina 26. maaliskuuta 2010 · Marius

today unused wood had to be moved below house.

img_0708.jpg

Day #178: House Connection Work & Chimney Finalization

Perjantaina 26. maaliskuuta 2010 · Marius

here are the pictures of the house connection work, which started in the mid of the week. freshly done on this day has also been the chimney finery.

img_0696.jpgimg_0697.jpgimg_0698.jpgimg_0700.jpg